PROVINCETOWN HARBOR PLAN 7/22/99
Table of Contents
November 11, 1998
I-A. Overview
I-A-1. A Plan for the Future of Provincetown Harbor
I-A-2. Planning Context
I-A-3. Organization of the Provincetown Harbor Plan
I-A-4. Limits of the Planning Area
I-B. Planning Framework: Overall Goals and Objectives
I-C. Summary of Principal Conclusions and Recommendations
I-C-1. Land Use
I-C-2. Water Use
I-C-3. Public Facilities
I-C-4. Proposed Local Regulatory Framework for Chapter
91
I-C-5. Long Term Plans
I-C-6. Implementation Framework
II. Review of the Planning Process
II-A. Preparation, Review and Approval Process
III. Summary of Existing Conditions
III-B. Physical Water and Land Conditions
III-B-1. General Description
III-B-2. Water Use
III-B-3. Land Use
III-B-4. Marine Structures and Coastal Features
III-B-5. Environmental Conditions
III-C. Regulatory Environment
III-C-1. Jurisdictional Context: Introduction
III-C-2. Zoning
III-C-3. Chapter 91
III-C-4. Municipal Harbor Plans
III-C-5. Federal Emergency Management Act Regulations
III-C-6. Harbor Regulations
III-C-7. Wetlands Regulations
III-D. Economic and Management Conditions
III-D-1. General
III-D-2. Provincetown Fishing Industry
III-D-3. Boat Repair and Maintenance
III-D-4. MacMillan Pier
III-E. Historic Setting and Social Context
III-F. Summary of Key Issues Based on Findings
IV. Summary of Planning Alternatives
IV-A. Purpose of the Planning Alternatives
IV-B. Summary of the Planning Alternatives
IV-B-1. Alternative 1: Improve the Existing Conditions
IV-B-2. Alternative 2: Encourage Waterside Potential
IV-B-3. Alternative 3: Encourage Landside Potential
IV-C. Conclusions of the Alternatives Phase
V. Planning Recommendations
V-A. Land Use
V-A-1. Land Use Patterns
V-A-2. FEMA Velocity Zones
V-A-3. Environmental Impacts of Land Use
V-A-4. Stormwater Management in Provincetown Harbor
V-A-5. Harbor Beaches
V-A-6. Summary of Land Use Actions
V-B. Water Use
V-B-1. Water Use Plan
V-B-2. Commercial Fishing
V-B-3. Aquaculture
V-B-4. Other Commercial Boating
V-B-5. Recreational Boating
V-B-6. Town Moorings
V-B-7. Navigation and Dredging
V-B-8. Water Quality
V-B-9. Summary of Water Use Actions
V-C. Public Facilities
V-C-1. MacMillan Wharf
V-C-2. Public Landings and other Publicly-owned Lands
V-C-3. Other Public Improvements
V-C-4. Summary of Public Facilities Actions
V-D. Regulatory Framework for Waterways Licensing
V-D-1. Introduction
V-D-2. Properties Within Chapter 91 Jurisdiction
V-D-3. Licensing Under the Amnesty Standards of the
Waterways Regulations
V-D-4. Licensing Under the 1990 Standards of the Waterways
Regulations
V-D-5. Effect of Plan on Pending and Future License
Applications
V-E. Guidance to DEP for Chapter 91 Licensing in
Provincetown Harbor
V-E-1. Objectives
V-E-2. On-Site Public Benefit Requirement
V-E-3. Off-site Public Benefit Requirements (Contributions
To the Harbor Access Gift Fund)
V-E-4. Additional Amplifications of Discretionary
Requirements
V-G. Summary of Recommended Actions for Water Access
and Enhancing Water-Dependent Uses
V-G-1. High Priority Actions
V-G-2. Medium Priority Actions
V-G-3. Long Term Actions
VI-A. Harbor Management Roles and Responsibilities
VI-A-1. Provincetown Harbor Committee
VI-A-2. Harbor Access Fund
VI-A-3. Provincetown Historic Rights-of-Way Committee
VI-A-4. MacMillan Pier Management Entity
VI-A-5. Other Existing Departments and Entities
VI-B. Chapter 91 Licensing Implementation
VI-C. Summary Matrix of Roles and Responsibilities
Summary of Sources and Additional Available Information
Appendix A, Provincetown Properties Presumed To Lie within Chapter 91 Jurisdiction Table
Appendix A Provincetown Properties
Presumed To Lie within Chapter 91 Jurisdiction List
Appendix B Recommended Parcel-Specific On-Site
Improvements
Appendix C
List of Figures
1. Planning Area Map, western portion
1. Planning Area Map, eastern portion
2. Existing Water Use, western portion
2. Existing Water Use, middle portion
2. Existing Water Use, eastern portion
3. Existing Land Use, western portion
3. Existing Land Use, eastern portion
4. Location of Public Access Points, western
portion
4. Location of Public Access Points, middle
portion
4. Location of Public Access Points, eastern portion
5. Environmental Conditions, western portion
5. Environmental Conditions, middle portion
5. Environmental Conditions, eastern portion
6. Existing Zoning
7. Existing Develoment within FEMA Velocity Zones
8. Proposed Water Use Plan, western portion
8. Proposed Water Use Plan, middle portion
8. Proposed Water Use Plan, eastern portion
9. MacMillan Pier, Existing Conditions (not included)
10. MacMillan Pier, Proposed Improvements (not included)
11. Provincetown Chapter 91 Guideplan: Region
Designations
12. Provincetown Historic Tidelands, west to
east #1
12. Provincetown Historic Tidelands, west to
east #2
12. Provincetown Historic Tidelands, west to
east #3
12. Provincetown Historic Tidelands, west to
east #4
Acknowledgements
Harbor Plan for the Town of Provincetown
Table of Contents
November 11, 1998
I. Summary of the Provincetown Harbor Plan
I-A-1. A Plan for the Future of Provincetown Harbor
Provincetown Harbor is an attractive focus of activity for the entire community which surrounds it. The Harbor area is a complex place that requires public attention to ensure appropriate use and a clean environment. The Provincetown Harbor Plan establishes practical steps to meet these goals. This Plan values the present character and activities within the Harbor area. Rather than seeking dramatic changes, the objective of the Plan is to enhance the Harbor through better management and by accomplishing a list of coordinated improvements.
The Plan envisions a future Provincetown Harbor with substantially greater
access and a more pleasant character along the waterfront for all of its
users. The Plan calls for many small scale improvements, each planned and
designed with respect for the special qualities of its particular circumstances
and the uses which will be served. Improvements will be achieved in part
by:
Improvements to all town landings and public access points.
A new set of guidelines and special license review process for harbor-edge
properties required to meet Commonwealth of Massachusetts Chapter 91 licensing
standards for public access and water-dependent uses. These guidelines
are tailored to Provincetown's special circumstances as a waterfront with
extensive Commonwealth tidelands largely filled by existing development.
In addition, the Plan includes improvements to the public wharves, bulkheads,
boat ramps and support infrastructure for commercial and recreational boating
through reconstruction and improvements. Both short-term and long-term
actions will continuously add to the safety and amenity of a harbor for
all sizes and types of vessels. Among the specific recommendations are:
Reconstruction of MacMillan Pier to correct deterioration and structural
deficiencies and better serve both current and future uses
Additional support facilities for small-boat commercial fishing
Improvements to the existing boat ramp and future construction of
a new boat ramp on a site to be determined through additional study
Use of existing land use procedures to protect water-dependent uses,
and the investigation of additional measures to help ensure appropriate
uses along the waterfront.
The Plan includes several management changes to improve coordination
of harbor activities and to make more efficient use of public resources.
Specific recommendations of the Plan include:
Creation of a Harbor Committee to ensure coordination of all aspects
of the harbor
Creation of a special management entity for MacMillan Pier to provide
for better management of a reconstructed pier so that it is not a deficit
for the town budget
Provincetown Harbor is a unique asset for the community, the region,
and the Commonwealth. Tucked inside a curling spit of sand at the outermost
reaches of Cape Cod, the harbor provides a deep natural anchorage and picturesque
setting that has attracted settlers, fishermen, tourists and residents
for hundreds of years. Like other harbors, it has mirrored a changing economy.
Once a major fishing and commercial port, the harbor edge was historically
lined with numerous piers and wharves. Commercial Street along the harbor's
edge served a vital marine-oriented economy and its related culture. While
it still serves a vital role as a marine harbor, the business of the harbor
is now largely related to tourism, which is the predominant economic activity
for Provincetown and Cape Cod.
This Plan for Provincetown Harbor establishes a reasoned approach to
the future use and management of Provincetown Harbor and its edges. The
Plan has been prepared by the Town of Provincetown to address numerous
existing problems and to establish consensus about the character and quality
of the harbor into the next century. The Plan has been prepared in concert
with the requirements for a Municipal Harbor Plan as recognized by the
Commonwealth of Massachusetts Office of Coastal Zone Management, to establish
a consistent regulatory approach to those lands and waters subject to Commonwealth
jurisdiction. The Commonwealth retains specific interests in the future
of the harbor for public access and water-dependent uses through M.G.L.
Chapter 91 (Public Waterways Act, 1866), and through the implementing regulations
(310 CMR 9.00).
The Plan more particularly responds to a specific list of issues raised in a participatory planning process as incorporated into a Scope for the Provincetown Harbor Plan. The Scope of the Plan was prepared by the Harbor Planning Committee, the group designated by the town to create this Plan. The Scope was also reviewed and approved by the Secretary of Executive Office of Environmental Affairs of the Commonwealth of Massachusetts, in keeping with the requirements of the State Municipal Harbor Planning process (301 CMR 23.00).
Five key issue areas have been addressed in this plan, and are reflected in its recommendations:
Preserving the Harbor's Built and Natural Assets;
Promoting Commercial Fishing and Aquaculture;
Providing for Diverse Vessel Use and Needs;
Assuring Public Access to the Shoreline for Recreation; and
Planning for Future Harbor Uses.
I-A-3. Organization of the Provincetown Harbor Plan
The elements of the Provincetown Harbor Plan have been organized to facilitate review and reference. This initial section of the Plan presents the fundamental goals and objectives of the plan and summarizes the principal recommendations regarding its future. Section II summarizes the planning process that has been employed to come to the conclusions contained in the Plan. Section III is a synopsis of the research concerning existing conditions that serve as the foundation for understanding the issues that are addressed by the Plan. Section IV recounts a key step in the planning process, during which potential alternative planning directions were studied and from which the conclusions emerged.
Section V incorporates the specific recommendations of this Plan. The
recommendations have been organized somewhat differently than the original
list of issues, to facilitate comprehensiveness and understanding of the
conclusion. The recommendations trace the implications of the Plan for:
Land Use
Water Use
Public Facilities
Regulatory Framework for Chapter 91
Long Term Plans
Section V concludes with Summary of Recommended Actions; this is a list
of prioritized actions that are intended for specific public actions and
expenditures.
Section VI is the Implementation Framework for the Plan. Rather than discussing what the Plan should accomplish, it describes recommendations on how the Plan should be accomplished. The implementation framework is summarized at the end of the section through a matrix that assigns responsibilities for each of the recommendations.
I-A-4. Limits of the Planning Area
The planning area used for this Harbor Plan includes all of the
land and uses immediately adjacent to the harbor within the town limits,
between the Cape Cod National Seashore on the west and the Town of Truro
on the east (see Figure 1. Planning Area Map). The Master Plan also includes
the waters and harbor bottom for an area that is enclosed by Long Point
to the South, the Long Point Dike to the west, the Provincetown waterfront
to the north, and a line generally connecting Long Point and the Provincetown/Truro
boundary to the east.
I-B. Planning Framework: Overall Goals and Objectives
The Provincetown Harbor Plan is based on a series of general goals and specific objectives. These goals and objectives are intended to inform every element of the Plan and to reinforce a coherent vision of the future of Provincetown Harbor. The goals and objectives are based on the results of public meetings, discussions, surveys, reports and recommendations that were developed over many years, and for which the Harbor Planning process has served as the focus.
Provincetown Harbor should consistently be recognized as a unique
public asset for which change should be carefully planned and implemented
to protect both its environmental and economic role.
Decisions concerning use of the harbor and its edges should seek to achieve a balance, allowing for multiple uses and seeking compatible relationships among them.
Marine-dependent uses should generally have priority over other uses
for land use and water use.
Provincetown Harbor is a scenic resource and activity center for tourism
and recreation; this role should be protected and enhanced.
The environmental quality of Provincetown Harbor should be managed,
monitored, and maintained to thoroughly protect its role as a natural and
clean asset.
Public access to and along the water's edge should be consistently
protected and enhanced.
Provincetown should strive to improve existing deficiencies in the
harbor for all existing uses, without seeking to significantly shift the
balance of uses in the short term.
Responsibilities should be reorganized to improve both the effective management of public facilities and the interests in the harbor.
The pattern of development along the Provincetown waterfront
is generally appropriate and desirable in terms of density, use, and scale.
However, increased provision for both access to the waterfront and access
along the water's edge should be reinforced wherever practical.
Land use impacts on water quality in the harbor should be minimized through correction of existing sewage and surface flow problems and the appropriate provisions in any future developments or improvements.
Harbor beaches should be maintained to reduce trash and detritus.
Facilities and support for the commercial fishery should be retained
and enhanced through programs and facilities that can be adapted to changing
needs of the industry.
A specific plan should be created for both on-site and off-site public
access for properties that are within the special jurisdiction of the M.G.L.
Chapter 91.
The needs of the small boat fishermen should be better accommodated
in Provincetown Harbor.
Provincetown Harbor should have improved access for trailered boats.
Opportunities for increased aquaculture should be pursued insofar
as they do not significantly interfere with existing patterns of use.
Support facilities, mooring and berthing opportunities, and boat ramp
facilities should be enhanced for recreational boaters.
A pro-active and planned program for maintenance dredging should be
implemented.
MacMillan Pier should be improved to correct existing deficiencies
and to serve future uses.
MacMillan Pier should be managed to continue to serve as the multiple-use
hub for public access to the water.
Town landings and publicly owned land along the waterfront should
be improved to provide better access and to accommodate increased public
use appropriate to each location.
Additional public access and amenities should be provided in areas
in which they are scarce, including portions of the East End.
The management of the town's waterfront assets (MacMillan Pier and
the mooring fields) should be self-supporting to the greatest extent practical.
Provincetown should establish a long-term goal of improving its facilities as a boating and cruising destination, by substantially improving the moorage and berthing potential for small boats through a comprehensive approach to breakwater and dredging improvements.
I-C. Summary of Principal Conclusions and Recommendations
Land Use Patterns and Regulations
Summary of Key Land Use Actions
Incorporate Harbor Plan recommendations into special permit, variance,
and similar reviews, including protection of water-dependent uses and limitation
of any expansion of commercial parking as a waterfront use consistent with
the Chapter 91 guidelines.
Establish a town working committee to consider proactive measures
for protecting and enhancing water-dependent uses including representation
from appropriate Boards and Committees.
Amend the zoning regulations regarding uses that support water-dependent
uses.
Seek funds and establish a process to study measures to protect properties
in the FEMA velocity zones.
Provide for continuation of water quality monitoring program. Design
a comprehensive stormwater management plan.
Enhance the removal of beach debris by providing additional assignment
of maintenance responsibility and funding to the DPW and by providing additional
trash receptacles.
Enhance the removal of beach debris by increasing volunteer activities
and increasing public awareness.
Include conditions on the removal of beach debris in relevant permitting
and licensing criteria.
In keeping with an overall goal of the Harbor Plan, there are several
recommendations concerning the importance of water-dependent uses. This
Harbor Plan recognizes that water-dependent uses should have reasonable
priority for use of the water's edge as a matter of policy and public right.
In part, this is a result of the Commonwealth's public use standards for
qualifying land areas, which have been codified in the regulations known
as Chapter 91. It is also in the best interest of Provincetown to support
water-dependent uses for reasons of economics and the historical character
of the community.
Most of the land use recommendations of the Plan are related to the
implementation of a program to provide improved conformance with the Chapter
91 protections for water-dependent uses and public access to the waterfront.
These recommendations are discussed at greater length in a separate discussion
below.
The Plan includes proposed improvements to publicly-owned lands that
would increase their potential for accommodating water-dependent uses.
These recommendations have been summarized in the discussion of Public
Facilities.
During the planning process, a review of existing zoning was undertaken.
Current zoning includes provision for water-dependent uses through a Harborfront
Regulation that applies to key portions of the central waterfront in which
water-dependent uses might be reasonably located. In general, it was concluded
that the regulations serve to protect the potential for water-dependent
uses. However, the regulation should be revised to accommodate some uses
that, although not water-dependent, serve to support water-dependent uses.
In particular, facilities that support the recreational boating industry
need to be better accommodated in existing zoning.
Environmental Impacts of Land Use
The Plan reinforces the existing town policies towards protection of
the harbor as an environmentally sensitive location. The Harbor Plan recognizes
the importance of the current program to correct water pollution problems
due to outfalls and failed subsurface sewage systems. The Harbor Plan recommends
proactive involvement of the town in programs to monitor water quality
and to pursue corrective measures to ensure high water quality.
Stormwater Management
Provincetown does not have a comprehensive stormwater management plan
at this time. This Harbor Plan recommends that such a plan be developed
and that, at the very least, existing water quality and storm sewer data
be supplemented with new data to characterize stormwater flow and to assess
the potential impact of septic systems on stormwater. In addition, if a
stormwater management program is developed, it should include and be based
upon a suite of multiple environmental indicators and not just on water
quality.
Harbor Beaches
The Plan calls for increased access and amenities for the public as well as useful marine-related improvements along several areas of the beach. The Plan recognizes that different beach areas have different uses. Specific recommendations for access and amenities are included in the sections of the report dealing with Town Landings and Commonwealth Tidelands, and in the section of the Plan that establishes standards for Chapter 91 compliance for qualifying properties and areas.
The Plan also identifies regions where beach erosion presents a problem
and suggests preliminary steps to prepare for future beach nourishment
in these and other areas. It further calls for an increased maintenance
program to remove trash and detritus from the harbor's edge.
Summary of Water Use Actions
Initiate and maintain an active program of aquaculture improvements.
Undertake a reorganized and improved new town mooring anchorage system.
Mark as off-limits for moorage or anchorage any areas requiring protection
for water quality and shellfish resource protection.
Designate more precisely all anchorage areas to reduce conflicts with
other uses in the harbor.
Set aside five of the town-owned moorings for emergency and storm
usage.
Mark wrecks to ensure safety.
Initiate a process for short-term and long-term maintenance dredging.
Secure alternate sources of funds for pump-out facilities.
Communicate to the National Park Service the recommendation that no
action be taken by the National Park Service that would reduce or alter
the activities recommended by this Water Use Plan.
Maintain commercial fishing facilities and correct deficiencies in
the configuration and condition of off-loading facilities through improvements
to MacMillan Pier.
Provide for improvements for other commercial boating as part of the
MacMillan Pier reconstruction and as part of boat ramp improvements.
Provide for an off-loading dock designed and dedicated for use by
small-boat fishermen with appropriate support facilities, including parking.
In the interim, expand the skiff dock and investigate the potential for increasing the number of vessels that can be tied up.
Commercial Fishing
The Plan reinforces the ongoing importance of commercial fishing in
the economic and cultural life of Provincetown. In the short term, the
fin fish industry is experiencing substantial stress due to resource supplies
and an emerging regulatory structure. As a result, there are shifts in
the requirements for both water-side and shore-side facilities. In the
long term, requirements remain difficult to predict. As a result, the Plan
recommends that commercial fishing facilities be maintained, and existing
deficiencies in the configuration and condition of off-loading facilities
be improved. In addition, the Plan recommends that MacMillan Wharf be improved
to provide for flexibility in its use for large boat commercial fishing,
including the potential for expansion.
The small boat commercial fishing industry is substantially under-served in regard to shore-side facilities. The Plan recommends that specific improvements be undertaken to provide substantially improved opportunities for tie-up, off-loading, repair and resupply. In addition, a boat ramp improvement project should be undertaken to allow access to more of the tidal cycle and improved accommodation of trailer parking.
Improvements are also recommended at the West End boat ramp to serve small boat fisherman, including the addition of tie-up floats. Moreover, steps will be taken to increase parking capacity, particularly for trailers, through physical improvements or management measures.
Aquaculture
The Master Plan calls for the general continuation of the existing pattern
of shellfish aquaculture, with emphasis on support for programs to resolve
pathology problems and to support shellfish propagation and productivity.
Potential expansion of shellfish beds should be pursued to the extent that
they do not conflict with the lobster fishery. The Harbor Plan also calls
for measures to support fin fish aquaculture in appropriate locations.
Other Commercial Boating
The Harbor Plan supports measures that increase the capacity for passenger ferry and excursion boats docking in the harbor. In general, the Plan supports measures that encourage a greater number of arrivals and departures of smaller ferry boats rather than the accommodation of infrequent arrivals of larger ferry vessels. The Harbor Plan also supports measures to substantially improve the shoreside accommodation of cruise ships.
Recreational Boating
The Harbor Plan supports measures that provide increased amenity and
safety for recreational boating. These measures should include the provision
of appropriately located dinghy docks, showers, laundry facilities, lockers,
and other facilities available for the transient boater.
Navigation
The Harbor Plan recommends a series of measures to improve navigability within the harbor. These recommendations include the continued monitoring of shoal areas and maintenance dredging in frequented areas of the Inner Harbor. The Plan also calls for the removal of any mooring floats within the harbor navigation fairways and channels, and the continued monitoring of these locations by the Harbormaster.
Summary of Public Facility Actions
Undertake the engineering analysis and design for the reconstruction
of MacMillan Pier to correct fundamental problems and to better accommodate
existing and future uses as called for in the Water Use elements of the
Plan.
Undertake a detailed study to implement a new MacMillan Pier Management
entity, in consultation with DEM, DEP and other appropriate state agenices.
Create a new MacMillan Pier Management entity.
Fund and construct MacMillan Pier improvements.
Undertake a planned program of public access and water-dependent capital
improvements as listed in the Plan.
Establish a planning process and reach a conclusion on an improved
small boat com- mercial facilities, including the best location, and pursue
funding for this improvement.
Establish a planning process and reach a conclusion on public fishing
pier locations and pursue funding for this improvement.
Establish a Right-of-Way Committee to confirm and protect existing
public access rights.
Establish a planning process and reach a conclusion on a new boat
ramp location and pursue funding for this improvement.
MacMillan Wharf
The Harbor Plan maintains the intention of Provincetown to preserve
the multiple-use function of MacMillan Pier. It reinforces the need to
reconstruct the Pier to redress its deteriorated condition. The Plan calls
for adequate accommodation of pedestrian traffic as well as flexible accommodation
of all water-dependent uses that generate adequate income to offset operating
costs, and contribute to capital funding of the improvements that may be
needed.
Public Landings and other Publicly-owned Lands
The Harbor Plan calls for a list of projects and improvements that would
serve to upgrade the public access areas to the waterfront. This list includes
improvements in paving, improvements to accommodate vehicle and boat access
and improvements to provide public amenities and the like. For all public
access points, a new and attractive signage system should be put in place
that indicates public access and amenities. This signage system could also
be used for public access within properties subject to Chapter 91 public
access requirements and agreements as discussed elsewhere.
Funding for improvements may come from a variety of sources . This Plan
envisions the use of a dedicated fund-the Harbor Access Gift Fund-administered
by the town. The fund would be financed through grant sources, Chapter
91 cash contributions that are channeled to the town, direct town contributions,
and other sources.
Other Public Improvements
Other public improvements recommended in the Harbor Plan include access and physical improvements to several areas along the water's edge.
There are few opportunities for public access to the water's edge along
significant portions of the Harborfront. This is generally true of the
entire East End, beginning approximately at Pearl Street and extending
to the Truro line, with several exceptions. The Plan also recognizes that
most of the property and improvements south of the Commercial Street right-of-way
in this area are located on historic upland, and that public access doctrines
that could permit perpendicular access to the water do not apply in many
cases. The Plan further recognizes that there are numerous informal access
paths and limited private accessways that have been secured through agreements
among property owners. The Plan recommends that increased public access
be provided in areas where there are current barriers through purchase
of easements, agreements, or other actions. Such improvements could be
funded, in whole or in part, by the Harbor Fund discussed above.
I-C-4. Proposed Local Regulatory Framework for Chapter
91
Summary of Actions Concerning the Regulatory Framework for Chapter 91
Establish Harbor Committee and delegate Planning Board responsibility
for local license review.
Establish memorandum of understanding for specific implementation
of the Chapter 91 actions if required in addition to the provisions of
this Plan.
Establish and approve final methodology for determining appropriate
on-site and off-site improvements and for calculating cash contributions.
Massachusetts' principal tool for protection and promotion of active
water-dependent uses of its tideland and other waterways is M.G.L. Chapter
91 (Public Waterways Act, 1866). Chapter 91 and the waterways regulations
(310 CMR 9.00) are administered by the Division of Wetlands and Waterways
of the Massachusetts Department of Environmental Protection. The mechanism
for regulation is a license that must be obtained by all property owners
or jurisdictions that occupy qualifying locations. The Chapter 91 regulations
apply to all of the existing tidal waters below low water mark in Provincetown,
and affects certain land and property above this line.
The Provincetown Harbor Plan incorporates special guidelines for Chapter 91 that are particular to Provincetown and allow for appropriate accommodation of site conditions, while fulfilling the public rights to access and use of the waterfront. These guidelines would apply to new Chapter 91 licenses or certain licenses considered as part of an amnesty provision that is intended to provide for pragmatic licensing of qualifying existing properties to which these regulations apply.
These guidelines define a detailed access plan that establishes the
extent of public access, amenities or water-dependent use accessories that
may need to be provided on qualifying properties. Where appropriate improvements
cannot be reasonably accommodated within these properties, the Plan makes
provisions for a cash contribution to a locally-administered fund that
would support off-site improvements to meet the same public access and
use goals.
The Plan includes a prioritized list of public actions that have been established specifically to improve water access. This list should serve as the guide for public improvements to further Chapter 91 regulatory goals on a community-wide basis.
Summary of Actions Concerning Long Term Plans
Authorize the Harbor Committee to continue planning efforts for long-term
improvements such as breakwaters and substantial dredging initiatives.
The Harbor Plan includes a series of long term goals for the Harbor,
and outlines a process for studying, reviewing, and implementing these
long term improvements. The long term goals of the Harbor Plan include
increased protection of the inner harbor mooring areas, expansion of these
areas through a dredging program, and the use of dredge material to provide
increased beach area in appropriate locations along central waterfront
areas that have experienced beach depletion or where private improvements
have encroached substantially on available beach areas.
I-C-6. Implementation Framework
Provincetown Harbor Committee
The Plan recommends the establishment of a Provincetown Harbor Committee
by the town that would provide for coordinated management of the harbor.
This Committee would meet regularly and be composed of representatives
of key departments, boards with jurisdiction over harbor and water-related
activities, and representatives of industries with interests in the management
of the waterfront. The Harbor Committee would be responsible for monitoring
the implementation of the Harbor Plan and preparing updates. The Committee
would provide recommendations concerning changes in the Harbor Regulations
and Shellfish Regulations. The Committee would make recommendations on
the disbursements of the Harbor Access Fund and on all capital improvements
relating to the waterfront other than as provided for elsewhere. The Committee
would also be responsible for certain local reviews of Chapter 91 license
applications.
MacMillan Pier Management
The Provincetown Harbor Plan recommends the creation of a new management
entity to be charged with the redevelopment and future operations of MacMillan
Pier. The mission of this entity would be to ensure that the operation
of the Pier is no longer a deficit-encurring activity for the town through
comprehensive and dedicated management of all associated operating costs
and revenues.
Other Existing Departments and Entities
The Plan envisions relatively minor changes in the roles and responsibilities
of other existing departments and boards within the town. The Harbormaster
would retain all current duties and responsibilities, other than the property
and operations management of MacMillan Pier. The Planning Board would be
relieved of certain obligations to review Chapter 91 licenses in favor
of the new Harbor Committee. Several departments and entities, including
the Town Manager's office would need to participate in ongoing planning
and implementation tasks, including participation in the new Harbor Committee,
and/or MacMillan Pier management entity.
Chapter 91 Implementation Process
As a Municipal Harbor Plan, the Provincetown Harbor Plan includes a
number of specific implementation mechanisms including:
A specific waterfront improvement plan to guide review and approval of Chapter 91 license applications as provided for in 310 CMR 9.00.
A mechanism for the funding of off-site improvements through cash
contributions for properties which cannot reasonably comply with the revised
improvement plan.
Institution of a locally administered water access fund into which
the contributions will be made.
Institution of a new entity, the Provincetown Harbor Committee, to
oversee and monitor the implementation of the plan and its periodic review
and amendment.
Designation of the Harbor Committee as the entity responsible for reviewing local Chapter 91 license applications for consistency with the Provincetown Harbor Plan, and preparation of recommendations to the Commonwealth, either independently or in conjunction with the Planning Board, if necessary.
Harbor Plan for the Town of Provincetown
I. Summary of the Plan
November 11, 1998
II. Review of the Planning Process
II-A. Preparation, Review and Approval Process
The Provincetown Harbor Plan has been prepared by a town-appointed
Harbor Planning Committee at the direction of the Board of Selectman of
the Town of Provincetown. The Harbor Plan represents the culmination of
several years of effort on the part of many participants in the planning
process, as summarized below.
The Harbor Plan is intended to fulfill two related needs. The first need is to resolve numerous local issues concerning both land and water use so that Provincetown Harbor can be better managed as a town resource in the future. The second need is to resolve special regulatory issues growing out of the Commonwealth's jurisdiction over qualifying tidelands (historic and current).
The Commonwealth of Massachusetts maintains public access rights to
qualifying coastal areas for "fishing, fowling, and navigation" through
M.G.L. Chapter 91 (Public Waterways Act, 1866). These rights are currently
regulated through the provisions of the regulations within the Waterways
Regulations (310 CMR 9.00, 1990). These regulations create numerous specific
requirements for the use and disposition of improvements on certain land
and flowed tidal areas within Provincetown. Several of the provisions of
the current regulations do not reflect the specific local conditions in
Provincetown, nor do they offer alternative methods for meeting the intent
of the regulations. An alternative method for establishing locally-appropriated
regulations is provided by the state in the form of a Municipal Harbor
Plan, which is approved by both the town and the Commonwealth. The special
requirements and process for preparation of a Municipal Harbor Plan are
specified in a separate but related set of regulations, Review and Approval
of Municipal Harbor Plans (301 CMR 23.00, December, 1994).
The town established a special Harbor Planning Committee in the early 1990's to develop a mooring and harbor plan. The mooring plan was completed in 1992 and continues to serve as a working document, as it is annually updated. The Harbor Planning Committee also undertook an extensive effort to survey town residents and harbor users on key issues. This resulted in the publication of a working paper entitled "Issues, Concerns and Opportunities" (September, 1994). The issues discussed in that paper informed the principle goals and objectives of this Harbor Plan. The issues were used to help create the list of key issues that were included in the Scope for this Harbor Plan.
It was decided the Harbor Plan should fulfill the special requirements
of a Municipal Harbor Plan consistent with the Commonwealth of Massachusetts
Requirements. Coordinating their efforts with the staff of the Office of
Coastal Zone Management, the Harbor Planning Committee drafted the Provincetown
Harbor Plan Scope in 1995, and submitted it to the Secretary of the Executive
Office of Environmental Affairs for approval. The Secretary's approval
was issued on December 13, 1995.
The town approved funds for the preparation of the Plan and in December, 1995 issued a Request for Proposals from consultants to assist the Harbor Planning Committee. A consultant team led by Cecil & Rizvi Inc. was selected. This team included the Urban Harbors Institute of the University of Massachusetts and Nucci/Vine Associates.
The preparation of the Harbor Plan was initiated in February 1996. The first steps in the process included interviews with relevant interest groups, agencies, and individuals. A public workshop was held on March 13, 1996, to discuss existing opportunities and constraints, and to help set the goals and objectives for the Harbor Plan. Subsequently, a Findings Report was issued discussing the existing conditions that had been investigated (May 8, 1996). A series of alternative approaches to the planning of the harbor were established through meetings with the Harbor Planning Committee and others. The alternatives were the subject of a public workshop (May 8, 1996) and the alternatives report was subsequently, issued taking advantage of the public input (June 6, 1996). The preferred plan was developed during the summer and early fall of 1996 and included three meetings of the Harbor Planning Committee.
The Draft Harbor Plan was completed in November, 1996. It will be the subject of public review and comment, including a public meeting on November 20, 1996. The Draft Harbor Plan will also be reviewed by the Harbor Planning Committee, the staff of the Office of Coastal Zone Management, and others. Based on the review and comments, a proposed Final Harbor Plan will be formally submitted for final review and approval to the Secretary of the Executive Office of Environmental Affairs. Public notice of a formal review period will occur at that time. Two public hearings have been planned on the Final Harbor Plan. In addition, the town meeting of April 1996 will constitute the required public hearing on the project, and approval by the town will be sought. Subsequently, any comments from the Secretary will be reviewed during a Consultation Session. It is anticipated that final approval of the Harbor Plan by the Secretary will occur late in the winter of 1997.
Two parallel planning efforts have also contributed significantly to
the research and conclusions of this Master Plan. The first was a research
effort conducted in 1995 by the Waterfront Access Field Project Team from
Tufts University. This is a program of the Urban and Environmental Policy
Department. The study was conducted at the invitation of the Town of Provincetown
by a team of Tufts faculty and students. The purpose of the study was to
inventory in detail the existing conditions of waterfront development as
it pertains to the Chapter 91 regulations, and to investigate public access
options and policy implications. Their extensive documentation and research
was a valuable contribution.
A second parallel effort was a special study of MacMillan Pier to examine its role in the regional economy and outline a revitalization approach and business plan for its future. This study was funded by a grant from the Massachusetts Development Finance Agency, and was conducted by a selected consultant team led by Cecil & Rizvi Inc. with FXM Associates Inc. (economics) and Nucci/Vine Associates Inc. (marine engineering). The results of this study have been incorporated into this plan where they are relevant.
The Provincetown Harbor Plan has been prepared through broad participation of many individuals and entities. The following is a partial list of the entities and individuals who have contributed to its preparation and the discussion of the issues and recommendations which have emerged.
Board Selectmen
Jane Antolini
Irene Rabinowitz
Custodio Silva, Jr.
Henry K. Evans
Elizabeth Steele-Jeffers
Harbor Committee
Gwen Billig, Chair
Al Davis
Dana Faris
George Hitchcock
Gordon Peabody
Dianne Thomas
Town Manager
Keith Bergman
Former Assistant Town Manager
David Goode
Marine Superintendent
David Ditacchio
Shellfish Constable
Robert Enos
Shellfish Committee
Mollie Benjamin, Chair
Director of Public Works
Joseph Borgesi, P.E.
Parking Administrator
Ernest Reppucci
Commonwealth of Massachusetts, Executive Office of Environmental Affairs
Trudy Coxe, Secretary
Office of Coastal Zone Management
Margaret Brady, Director
Dennis Ducsik, Tideland Policy Coordinator
Laurel Rafferty, Harbor Management Coordinator
Truman Henson, Jr., Cape & Isalnds Regional Coordinator
Department of Environmental Protection
Greg Carrafiello
Participants in Interviews and Special Meetings
Candy Collins-Bowden, Chamber of Commerce
A. Brown, Victory Fisheries, Shellfish Committee
Robert Burns MacMillan Wharf Boat Owners Association
P. Clay, Regional Anthropologist, NMFS
R. DeConti. Director of Conservation, Center for Coastal Studies.
Ray Duarte, Oceanic Seafood Company.
C. Joyce. Project Manager, Army COE.
Patricia Lemme
S. Murowski
Joy McNulty, Zoning Board of Appeals
Stephan Nofield, former Economic Coordinator
Thomas Osowski, Assistant Harbormaster
John Santos, Flyers Marina and Town Conservation Commission
Alix Ritchie, Representative. to Cape Cod Commission
L. Spenly, Port Agent for Provincetown
Consultant Team
Cecil & Rizvi, Inc:
Steven Cecil, Project Director
Leslie Bain, Planner
Nancy Coleman, Land Planner
Urban Harbors Institute:
Jack Wiggin, Assistant Director
Chantal Lefebvre, Research Analyst
Nucci/Vine Associates, Inc:
David Vine P.E.
Jean Haggerty
Tufts University Access Field Team
Kristen Bishop
Andrew Hargens
John Hoey
Michael Rotondi
Harbor Plan for the Town of Provincetown
II. Review of the Planning Process
November 11, 1998
III. Summary of Existing Conditions
The initial product of the Provincetown Harbor planning process
was the Findings Report. The forty-three page document served as a basis
for the development of alternative approaches to the harbor's future, and
provided the framework for developing the Harbor Plan. This Findings Report
included not only the mapping of physical conditions, but also the documentation
of the regulatory, economic and social context of the harbor. Included
in the findings were discussions of physical land and water conditions,
the regulatory environment, economic and management conditions, the social
and historical setting, and the key issues that had been identified at
the public meeting held as part of the planning process. This section of
the Provincetown Harbor Plan summarizes and updates relevant portions of
the Findings Report to provide a reference for the conclusions and recommendations
of the Plan.
III-B. Physical Water and Land Conditions
The Town of Provincetown is located at the northernmost tip of Cape
Cod in southeastern Massachusetts. It is bordered by the Town of Truro
to the east, Cape Cod Bay to the south and to the west, and the Atlantic
Ocean to the north. The tidal coastline of Provincetown consists of 21.3
miles, most of which lies within the Cape Cod National Seashore. As noted
in Section I, the harbor planning area includes all of the land and uses
immediately adjacent to the harbor within the town limits, between the
Cape Cod National Seashore on the west and the Town of Truro on the east.
The Harbor Plan also includes the waters and harbor bottom for an area
that is enclosed by Long Point to the South, the Long Point Dike to the
west, the Provincetown waterfront to the north, and a line generally connecting
Long Point and the Provincetown/Truro boundary to the east.
The water's edge within the planning area represents a long crescent, with varying characteristics. Long Point is built from coastal dunes and is open space that is used recreationally and serves to protect Provincetown Harbor from southerly winds. The Long Point Dike is a continuous stone structure that divides the harbor to the east from marshy tidal flats to the west, and connects Long Point to the western edge of Provincetown, where private and municipal lands meet the Cape Cod National Seashore. Proceeding in an eastern direction, the waterfront is nearly completely developed to the Truro Town line. Commercial Street is a public way that runs parallel to the waterfront for the entire length of the harbor edge. From Stevens Point to the intersection of Commercial and Bradford Streets, a single row of properties generally stretches between the water's edge and Commercial Street. From this point to near its intersection with Berry Lane, Commercial Street approaches the water's edge. From this point to the Truro town line, Commercial Street turns inland. In this area, secondary streets and private ways often serve multiple properties that stretch between the waterfront and the harbor's edge.
In general, the edges of the water throughout the planning area are intertidal beaches of various widths. Major exceptions include the Long Point Dike and the bulk-headed edge of the Municipal Parking Lot at the Town Center. Numerous smaller bulkheads have been created to extend or protect specific parcels, some of which represent the water's edge at high tide. There is an extended length of stone rip-rap along the shore where Commercial street meets the beach.
Water depths generally follow a shallow gradient from the beaches to
deeper water, with two significant exceptions. Consistent currents maintain
a deep water channel inside of Long Point. A combination of natural water
depths and maintained channels reach towards land at the center of Provincetown,
and serve the three principle remaining piers that stretch into the harbor
(the Coast Guard Pier, Fisherman's Wharf, and MacMillan Pier). A long stone
breakwater protects the inner harbor area, running parallel to the water's
edge in an east/west direction.
There are a variety of harbor water uses including tourism, transportation,
recreational uses, fishing, and commercial uses (see Figure 2. Existing
Water Use (2 pages)). This study has reviewed pertinent information concerning
the following list of the harbor's water uses.
Commercial and recreational fishing Sailing
Mooring for all types of vessels Boat storage
Pleasure boating Diving
Bird watching Lobstering
Boat repair Ferries
Commercial charter Waterfront events
Boat launching Coast Guard operations
Kayaking Cruise anchorage areas
Swimming Seafood off loading
Marinas Sun bathing
Coastal research Aquaculture
Parasailing Jet skiing
Water skiing Harbor shuttles
Rowing Beach strolling
Fueling
The following is a summary of the key uses that were considered in detail
during the planning process.
Moorings
There are generally 3 categories of moorings within Provincetown Harbor:
(1) individual moorings, (2) rental moorings, and (3) Federal off-shore
moorings. The town issues approximately 470 individual moorings annually,
a number that has grown steadily. The moorings are located behind the breakwater
and throughout the harbor. Rental moorings are those for which any type
of fee is charged, including marinas, yacht clubs, hotels, inns and guest
houses as part of their facilities. The town issues approximately 160 rental
moorings annually. There are 40 federal moorings located off-shore of the
harbor which are available for mooring of larger vessels having Federal
permission.
Mooring rules and regulations comprise Chapter 2 of the Town of Provincetown
Harbor Regulations, adopted in 1991 and subsequently amended. The regulations
include provisions for permits and fees, mooring equipment, water quality,
enforcement and allocation.
Water-based Transportation
Traditionally, Provincetown was served by both passenger and cargo vessels.
While the extension of highways along the entire length of Cape Cod dramatically
reduced the dependence of Provincetown on water-based transportation, it
is still substantial, and may grow in the future.
There are currently four passenger ferries/excursion boats that serve Provincetown. The Baystate Cruise Company operates an 1,100 passenger vessel between Boston and Provincetown from late spring to the early fall. This boat docks along MacMillan Pier. Fisherman's Wharf hosts two boats that connect Provincetown to Gloucester and Plymouth, with capacities of approximately 250 and 500 passengers respectively. Sea Ventures operates a ferry between Marina Bay in Quincy and Provincetown. There are currently no freight boats serving Provincetown, nor is there a facility that can accommodate freight. There may, however, be a small potential market for this service during the peak tourism season, although its feasibility has not been demonstrated.
Boatyards
There are two boat repair services in the harbor, Flyer's Boatyard and
Taves' Boatyard. Flyer's Marina uses two marine railways for launching
boats and a fork lift off the dock for smaller boats. There are no travelift
structures for boat outhaul located within the harbor. Boat repairs have
been on a decline due to the general depletion of the town fishing fleet.
There is also a simple piling and beam framework on intertidal bottom just
east of MacMillan Pier that is used for occasional tie-ups and repairs
at low tide of vessels on an informal basis as a public facility.
Marinas and Private Moorings
The single major marina facility is Provincetown Marina and Moorings, located off of Fisherman's Wharf. Provincetown Marina provides full marina services, with approximately 30 slips and 110 rental moorings. Located on the west end, Flyers Marina has no slips, but has 50 rental moorings, and provides many marina services. The two mooring facilities each have launch services.
Marine Pump-out Facilities
The town has a 300 gallon pumpout boat servicing the harbor. The boat
is provided on an as-called basis through the Harbormaster's office.
Courtesy Float and Dinghy Dock
A small courtesy float is provided by the town along the southerly edge of the Municipal Parking lot. This float serves temporary docking needs of small boat commercial fishing. The courtesy float also serves the short-term needs of recreational boaters. Finally, the courtesy dock serves the occasional landings of cruise ship passengers. The town has a skiff-dinghy dock located on the east side of MacMillan Wharf, which is available to vessels less than 16 feet on a transient basis. Seasonal skiff dock permits are available through the Harbormaster.
Wetland Resources
The Wetlands Conservancy Program is currently updating wetland resources for inland and coastal wetlands of Provincetown. Colored "interim" plan designations were provided for use during the planning process with the understanding that the data is preliminary and should not be used to indicate legal wetland delineations. The Environmental Conditions Map illustrates the general location and relationship of wetland resources to other harbor features.
The following table and the Existing Land Use map present a breakdown
of the land uses in the Provincetown Harbor planning area. The land use
data in this Table is from the database maintained by the Cape Cod Commission,
which was compiled from the Provincetown Assessor's records.
Table 1. Summary of Land Use in the Harbor Planning Area
| Land Use |
|
| Single-family residential | 13.53 |
| Multi-family residential | 16.66 |
| Office and retail trade | 6.96 |
| Motels and restaurants | 8.99 |
| Storage warehouses and distribution | 2.16 |
| Institutional | 10.20 |
| Commercial parking lots | .36 |
| Vacant land | 2.24 |
| TOTAL | 61.10 |
Water-dependent Land Uses Along Provincetown Harbor
There are two areas along Provincetown Harbor which feature water-dependent
uses (see Figure 3. Existing Land Use). The first area is located in the
"West End" of Provincetown and includes two water-dependent industrial
uses: a boatyard and boat storage and the U.S. Coast Guard facilities.
The second major area is located near the center of the town and is comprised
of a mix of commercial (58%), residential (19%) and mixed use (23%) and
includes the water-based activities centered around MacMillan Pier. The
major water-dependent activity on shorelands in this area is a working
area on the beach where boat repair and boat storage take place.
As in most other areas, the market demand for water-dependent uses is
relatively weaker than demand for nonwater-dependent uses, such as residential
and retail. As a result, over time higher valued nonwater-dependent uses
have tended to displace water-dependent uses. In Provincetown as elsewhere,
the space occupied by water-dependent uses has been in decline over the
years. A review of historical maps and documents and interviews with Provincetown
residents reveals a consistent and substantial long-term decline in the
number and variety of businesses and in the amount of waterfront area dedicated
to commercial fishing and vessel-related uses (see all town Master Plans
and all studies of the commercial fishing industry as noted in the Summary
of Sources and Additional Available Information). No data was discovered
that would suggest sources of demand for water-dependent economic uses
which would justify land values exceeding those established by nonwater-dependent
uses for the land which predominates today without substantial public subsidy.
Of particular use in this consideration was the General Economic Base and
Micro-Enterprise Feasibility Study. (McDermott/O'Neill & Associates
and The Howell Group. December, 1995.) This study confirmed the predominant
role of tourism as the basis for the local economy.
It is important also to take into account the fact that the harborfront
of Provincetown is nearly entirely built-out with nonwater-dependent uses
that are on small lots. A complete review of assessor's maps and site confirmation
of parcel land use was undertaken which confirmed this observation. Under
these conditions, land assembly would be extremely difficult for any water-dependent
use requiring relatively large and contiguous sites, even if land values
were not a dominant factor.
A Provincetown Transportation Center Study was recently completed by
Cecil & Rizvi and EarthTech for the Town of Provincetown. The plan
was approved at the 1996 Town Meeting. Existing conditions relating to
transportation were documented, and a series of recommendations made for
improving town-wide circulation, parking and signage. The plan called for
improved conditions for each of the transportation modes through better
circulation patterns and improved physical accommodations. The plan also
includes proposed enhancements to the townscape. Key elements of the plan
relevant to the Harbor Plan include:
Provincetown Multi-modal Transportation Center - Mass transit buses,
shuttle buses and tour buses will be accommodated in a new multi-modal
transportation center along a realigned Ryder Street extension, and include
provisions for waiting shelters, bicycle racks and storage, and relocated
public restrooms.
Improvements for Marine Uses - The plan recommends substantial improvements
for pedestrian access to the piers and floats, retention of key access
for commercial boats, as well as the construction of a Harbormaster's office.
Open Space Improvements - Key open space improvements include new and expanded park space along the waters edge of the Municipal Parking Lot, new landscape and streetscape improvements at Lopes Square, and additional plantings and streetscape improvements in the Municipal Parking Lot and at several intersections.
Pedestrian Improvements - Improved and widened sidewalks and improved
crosswalks would be added in numerous locations, including the intersection
of Bradford and Standish Streets, along Standish Street as it approaches
the waterfront, and along Ryder Street between Commercial Street and the
Municipal Parking Lot, and as part of the Municipal Parking Lot.
III-B-4. Marine Structures and Coastal Features
Provincetown Harbor is a natural deep harbor with a mean tidal range
of 9.1 feet, and prevailing winds from the south/southwest. The central
harbor is defined by the waterside Commercial Street shoreline to the north,
the Corps of Engineers Dike to the west and the Long Point Peninsula to
the southwest.
The harbor is entered from the west. A stone armored breakwater affords protection from the southeast to MacMillan and Fisherman's Wharves and moorings. Draft behind the breakwater is generally less then 15 feet. In the open harbor waters seaward of the breakwater, a sizable anchorage area has drafts from 20 to 60 feet.
A 300-foot wide Federal Channel extends seaward of the breakwater where
it divides into one section to the Coast Guard station and the other to
MacMillan Pier.
The historic shoreline apparently was just seaward of Commercial Street
until manmade filling extended it to its present location. This shoreline
has remained relatively constant over time, but some shoaling has occurred
along both ends of the Federal Breakwater and around piers. The Corps of
Engineers has done some recent dredging on the east end of the channel.
The longshore drift is generally to the west. Perpendicular beach obstructions generally cause cut-off of drift resulting in mounding in some areas. Structures, such as storm drain outfalls, tend to get sanded in. There is no formal beach maintenance program.
MacMillan Pier
MacMillan Pier is a 1,450 linear foot, concrete deck, timber pile supported
pier, owned and operated by the town. This pier serves as the hub of the
waterfront. The 950 linear foot causeway is primarily utilized on the west
side. Fishing vessels utilize the outer end on the east side, and transient
boats generally use the south and west ends. Uses of the pier include the
following:
Berthing is provided for 19 fishing vessels off of 2 finger piers
on the east side. The piers were originally designed to accommodate 36
boats.
Members of the MacMillan Pier Float Owners Association lease 11 float
spaces from the town. Floats are owned by individual Association members.
Ten are located on the east side and one is on the west side. They provide
a variety of summer recreation and sport uses including a significant whale
watch fleet.
There are two private fish off loading facilities where fish is iced
and immediately shipped out: Oceanic Seafood Corporation and Cape Cod Bay
Fisheries, Inc. These operations occupy one building and their truck trailers
park on the Pier.
Additional off-loading privileges have been extended to an organization of commercial fishing boat operations, the Bayview Fisheries Cooperation Trust.
The Harbormaster Office occupies a building on the Pier.
Dockage for ferry and excursion boats.
The dinghy dock is located on the east side of the Pier.
The Pier also serves as the only means of access to an "out" parcel, which is occupied by a small two-story building on piles and associated floats. The building is occupied by the Whydah Museum, which is a tourist destination and displays artifacts from this historic vessel. The floats which surround the parcel serve as a small private marina.
The pier was constructed in 1955 and funded jointly by the town and Commonwealth. It has electric and water service, and two holding tanks. Neither public restrooms nor fueling or boat outhaul facilities are available on the Pier.
The pier is currently in need of structural repairs. There is a State Court order currently in effect restricting vehicular traffic on the pier and requiring a phased program of improvements. As a task in their services for the recent Draft MacMillan Pier Redevelopment and Business Plan (Cecil & Rizvi Inc., 1996) funded by the State, Nucci Vine Associates Inc. undertook a brief analysis of pile capacities that suggest that the entire pier construction may not be sufficient to support modern truck loads (HS20 loading standards). This limits access to the pier by a variety of truck sizes important to retaining commercial fishing, off-loading, and fish packing operations. In addition, it may be unsafe for fire trucks to be able to safely reach the entire pier and any boats moored along its edge. Subsection 2000-8881 of the Seaport Bond Bill provides $7,500,000 of currently unfunded authorizations for plans, repairs and improvements to MacMillan Pier .
Fisherman's Wharf
Fisherman's Wharf is a 1,400 linear foot concrete deck pier on timber
pile It is privately owned, and provides marina and mooring services. The
pier includes several buildings which support the marina, day trip facilities,
and the launch service. The owner has applied for additional permits for
increased recreational usage.
Coast Guard Pier
This 1,150 foot long pier is constructed of timber piles with a concrete
deck, with a wave break at far end. The pier provides berthing for Coast
Guard vessels. The Coast Guard also has 5 moorings.
Federal Breakwater
Completed in 1972, this 2,500 linear foot armored stone breakwater has
a crest elevation of 15.5 (MLW). Because of the orientation of the breakwater,
only limited protection is provided for predominant winds from the southwest.
Federal Rubblestone Dike
The Federal rubblestone dike runs 6,150 linear feet from Stevens Point
across to Wood End. It was constructed by the Corps in 1972, and provides
a recreational and fishing area for the public.
Town Landings
There are eleven designated public Town Landings: Kendall Lane extension,
Washington Avenue extension, Pearl Street extension, Freeman Street extension,
Gosnold Street extension, Court Street extension, Atlantic Street extension,
Good Templar Place, Franklin Street extension, West Vine Street extension,
and West End Boat Ramp. In addition, there are four non-designated landings
owned by the town: Kendall Lane, Johnson Street, the extension of Washington
Street, and the West End parking lot. The public use of the landings is
limited to pedestrian and small boat access to beach (see Figure 6. Location
of Public Access Points (2 pages)).
Boat Ramp
The town-owned West End Boat Ramp is restricted by tide and lack of
support floats, as well as limited parking. Although it has been considered
in the past, the town has not pursued State Public Access Board expansion
or repair of the facility to date.
III-B-5. Environmental Conditions
Water Quality
The coastal marine waters of Provincetown are classified 'SA', according
to CMR 314. SA-classified waters are suitable for any high quality water
use, including bathing, swimming, and shellfishing. The Massachusetts water
quality standards for SA-classified waters are as follows:
Table 2. Water Quality Criteria and Provincetown Waters
| Item | Water Quality Criteria |
| Dissolved Oxygen | Not
less than 6.0 mg/l at unless background conditions are lower.
|
| Temperature | Not
to exceed 85 F (29.4 C) with daily mean of 80 F (26.7 C). Rise in temperature
due to discharge not to exceed 1.5 F (0.8 C)
|
| pH | 6.5
to 8.5 standard units.
|
| Fecal
Coliform
Fecal Coliform (contd.) |
In
waters approved for shellfishing: not to exceed MPN* 14 col./100 ml; 10%
of samples not to exceed a MPN of
43 col./100ml. In waters not designated for shellfishing: not to exceed 200 organisms in any representative set of samples; 10% of samples not to exceed 400 col./100ml.
|
| Solids | Waters
must be kept free from floating, suspended, settleable solids in concentrations
or combinations that would impair any assigned use to this class, that
would cause aesthetically objectionable conditions or that would impair
the
benthic biota or degrade the chemical composition of the bottom.
|
| Color and Turbidity | Waters
must be free from color and turbidity in concentrations or combinations
that are aesthetically objectionable or would impair any use assigned to
this class of waters.
|
| Item | Water Quality Criteria |
| Total phosphate | Not
to exceed an average of 0.07 mg/l as P during any monthly sampling period.
|
| Ammonia | Not
to exceed an average of 0.2 mg/l as nitrogen during any monthly sampling
period.
|
| Taste and Odor | Non allowable |
The Center for Coastal Studies has been steadily monitoring the water
quality in Provincetown's coastal waters, sampling for dissolved oxygen
and fecal coliform concentrations. There is limited data documenting the
state's other water quality criteria in Provincetown.
In 1996, average concentrations of dissolved oxygen demonstrated little
variability over the course of the sampling season and were maintained
above the state and federal minimum standard of 6.0 mg/l - indicative of
a healthy ecosystem. Rapid tidal flushing in the harbor is the predominant
physical factor maintaining these oxygen concentrations. The lowest average
dissolved oxygen levels in 1996 were recorded at the Provincetown Inn (6.9
mg/l) and the Boatslip (6.6 mg/l). The reasons for the lower concentrations
at these sampling stations are unknown.
Although the harbor-wide geometric mean for bacteria concentrations
was generally low in 1996, peaks in fecal coliform concentrations, exceeding
the state standard of 14 organisms/100ml, were measured at various sampling
stations throughout the year. Concentrations in excess of the regulatory
standard indicate that the waters should be closed to recreational use
and to shellfishing.
The major concerns regarding the quality of harbor waters are septic
disposal and debris (see Figure 5. Environmental Conditions (2 pages)).
In 1994 a study by a citizens group, Woods Hole Oceanographic Institutes
Sea Grant New Initiative Program, and Massachusetts Coastal Zone Management,
identified the 6 major contributors as:
Land Generated Marine Debris, from mishandled garbage;
Discharge Pipes, mostly from street drains;
Sewage Discharge, from waterfront septic systems and boats of all
sizes;
Boat Generated Marine Debris, from mishandled garbage;
Marine Nets and Lines, lost at sea, and deliberately tossed overboard;
and
Public Awareness/Information, (or the lack of) relating to debris
impacts, disposal facilities, and the appropriate means of handling garbage
in a coastal setting.
In response to the water quality problem caused, in part, by the existing
subsurface wastewater disposal systems, the town is in the early stages
of preparing a wastewater plan. The scope for a study which will include
an assessment of existing conditions, a projection of future wastewater
needs, and the development of alternatives to remedy the situation, is
currently being prepared for the town by its consultants.
Water in Provincetown is derived from municipal wells. town storm drainage
facilities include a series of variable aged piping and catch basin systems.
There are currently outfalls that discharge into Provincetown Harbor, contributing
to the water quality problems in the harbor.
Sewage/Title V
Provincetown has no municipal sewage collection system. Residences and other users must have on-site subsurface disposal systems. Subsurface sewage disposal is regulated by the State Environmental Code, Title V (310 CMR 15.00), which outlines the minimum requirements for the subsurface disposal of sanitary sewage.
Much of the Commercial Street waterside buildings east of MacMillan Pier are located in portions of FEMA V Zones. Title V has specific requirements for acceptable standards to be met for subsurface system to be sited in V Zones. Many of the existing subsurface systems in these areas would not be acceptable under current Title V standards. Title V enforcement occurs when systems are repaired or existing structures are altered. Water pollution from failing subsurface sewage systems has been a long-time concern in Provincetown, and the town is about to initiate a phased investigation recommending an overall wastewater strategy for the town.
III-C-1. Jurisdictional Context: Introduction
The waterfront is subject to regulatory authority of the local, state, and federal governments. Through its Zoning By-Law the city regulates uses, density and dimensions of development along the shoreline. It also regulates wetlands through its General Wetlands Ordinance.
The State exercises regulatory authority over the alteration or use
of both filled and flowed tidelands under Massachusetts General Laws Chapter
91, the Public Waterways Act. The purpose of this law and the waterways
regulations (310 CMR 9.00) adopted to implement the law is to protect the
public's interests in the waterways. All existing and new work such as
piers, wharves, floats, retaining walls, revetments, pilings, and some
waterfront buildings require Chapter 91 authorization.
The federal government, through the U.S. Army Corps of Engineers regulates shorefront activities including dredging and filling in or near coastal waters and structures below the mean high water mark (Section 404 of the Clean Water Act and Section 10 of the Rivers and Harbors Act).
There are four zoning districts in the Harbor planning study area, the land-side of which is defined as the area south of Commercial Street extending from the rotary at the west end to the convergence of Commercial and Bradford streets at the east end (see Figure 6. Existing Zoning (2 pages)). The four districts are Class B Residential, Class G Residential, Class W Residential, and Class R Commercial.
The following table summarizes the major uses allowed in each
of these districts. As is evident from the table, Provincetown's zoning
generally follows a conventional cumulative scheme. This scheme specifies
that allowed uses in more restrictive zones are carried over through the
less restrictive zones. Common concerns with this type of zoning, particularly
for the least restrictive district, are potential use conflicts and diminished
predictability of future land use. In the case of Provincetown's commercial
district, however, the result appears to be a healthy and vibrant mix of
uses. For the study area, the Provincetown zoning map reveals a traditional,
concentric pattern of progressively more restrictive districts surrounding
the downtown core commercial district.
Table 3. Major Uses Allowed by Right (Y) or by Special Permit (BA) from the Board of Appeals in the Four Zoning Districts of the Harbor Planning Study Area
| USES |
|
|
|
R |
| RESIDENTIAL | ||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
||
|
|
|
|
|
|
| BUSINESS | ||||
| Business or prof offices |
|
|||
| Hotel, motel, inn |
|
|
||
| Retail sales or service | ||||
| neighborhood |
|
|
|
|
| art gallery |
|
|
||
|
|
|
|||
| Restaurant, bar |
|
|||
| Parking lots |
|
|
|
|
| INDUSTRIAL | ||||
| Seafood processing |
|
|||
| Boat building, repair, overhaul |
|
|
||
|
|
|
|
|
|
|
|
|
|
||
| Transportation terminal |
|
|||
| INSTITUTIONAL | ||||
| Museum |
|
|
||
| Municipal use |
|
|
|
|
| Aquaculture |
|
|
|
|
| Artists studio |
|
|
|
|
Table 4. Dimensional Requirements for the Four Zoning Districts of the Harbor Planning Study Area
|
|
||||||||
|
District |
Min Lot Area |
Min Lot Frontage |
Front Yard |
Side Yard |
Rear Yard |
Max Lot Coverage |
Height in feet1 |
Stories |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Commercial Business and Industrial Development.
According to Section 3000 of the Provincetown Zoning By-Laws, in the
Commercial R district, the following requirements apply to new commercial
business and/or industrial developments; conversion of existing premises
to commercial or industrial use; construction or alteration of premises
containing these uses is greater than 50% of the floor area; developments
of more than 2,000 square feet of total retail space (interior and exterior)
or containing three or more retail, wholesale or service units. Key requirements
pertaining to the Harbor Plan include lot coverage (no more than 40% of
the total lot area), and green area (a minimum of 30% of every lot regardless
of size).
Harbor Setback
Section 1314 of the Provincetown Zoning By-Laws prohibits any structure
other than a pier, wharf or other facility requiring waterfront contact
to be constructed within 35 horizontal feet of mean high water of any salt
water body.
Harborfront Regulation
Section 3600 of the Zoning By-Laws establishes a "Harborfront Area"
overlay zone. The Harborfront area is defined as that area which is either
more than 195 feet seaward of the northern edge of Commercial Street in
the Commercial R district or seaward of the mean high water line, or both.
The regulation is designed to give special consideration to water-dependent
uses. Uses allowed by right (sec. 3620) in the harborfront area are primarily
water-dependent, e.g., marine services, boat sales; boat building, repair,
and storage; commercial beach. There are also two categories of special
permit uses. Section 3621, passed during the October 1996 Special Town
Meeting, allows several types of nonwater-dependent retail and restaurant
uses and parking lots by special permit. Section 3630 also allows by special
permit, a number of other water-dependent commercial and industrial uses
and selected cultural and recreational uses. In approving special permits
under both subsections, the Zoning Board of Appeals must include a determination
that the use:
1. interrelates productively with other waterfront activities,
2. makes efficient use of harbor frontage,
3. improves opportunities for visual and pedestrian access; and, in addition, for those uses under subsection 3630:
4. determines that the operating costs of the proposed use would be substantially greater for any but a waterfront location,
5. effect on town's infrastructure to service others, and
6. improves or maintains harbor water quality.
According to the building inspector's office, there have been very few projects reviewed under the provisions of Section 3600 because there has been very little development activity in recent years in the area subject to this section of the regulations.
Massachusetts' principal tool for protection and promotion of
active water-dependent uses of its tideland and other waterways is M.G.L.
Chapter 91 (Public Waterways Act, 1866). Chapter 91 and the waterways regulations
(310 CMR 9.00) are administered by the Division of Wetlands and Waterways
of the Massachusetts Department of Environmental Protection.
The Chapter 91 statute was amended in 1983 with new substantive and
procedural requirements in order to ensure that tidelands-both presently
flowed and formerly flowed tidelands-are utilized only for water-dependent
uses or otherwise serve a proper public purpose. Major revisions of the
waterways regulations followed in 1990. Key provisions of those amendments
promote water-dependent use of the shoreline; preserve and promote public
access; and encourage local involvement in Chapter 91 licensing decisions
through municipal harbor plans. A companion set of regulations governing
the development and approval of municipal harbor plans was also adopted
that same year (see below).
With the intent of bringing coastal properties into compliance with
Chapter 91, the 1990 revisions of the waterways regulations included an
amnesty provision applicable to unlicensed structures or fill in existence
and in use since January 1, 1984 (and without any substantial alteration
or change in use since that date). Amnesty license applications are subject
to the Chapter 91 Waterways Regulations that were in effect prior to October
4, 1990 (the effective date of the 1990 revisions) which are generally
less stringent, impose lesser fees, and provide longer terms than those
now in effect. The amnesty period expired October 4, 1996.
Activities Subject to Chapter 91
Chapter 91 authorization is required for placement of fill, building
of structures, and dredging in areas identified above. Types of structures
include: piers, wharves, floats, retaining walls, revetments, pilings,
bridges, dams, and waterfront buildings (if on filled lands or over the
water). A new license also may be required if there has been a structural
change or change in use of a previously licensed structure. The placement
of temporary rafts, floats or moorings in the waterway do not require a
Chapter 91 license, but must receive an annual permit form the harbormaster
(see Provincetown Harbor Regulations).
In general, uses licensed under the waterways program must either be
water-dependent or "serve a proper public purpose which provides greater
benefit than detriment to the rights of the public in said lands."
Water-dependent Uses
Water-dependent use is defined in §9.12(2) of the Chapter 91 regulations. In general, a water-dependent use is one that requires direct access to or location in tidal or inland waters, and therefore cannot be located away from said waters. A full definition of water-dependent uses can be found in the regulation. The following is a list of water-dependent uses that are likely to apply to Provincetown:
Marinas, boat basins, channels, storage areas, and other commercial or recreational boating facilities;
Facilities for fishing, swimming, diving, and other water-based recreational activities;
Parks, esplanades, boardwalks, and other pedestrian facilities that promote use and enjoyment of the water by the general public and are located at or near the water's edge, including but not limited to any park adjacent to a waterway and created by a public agency;
Aquariums and other education, research, or training facilities dedicated primarily to marine purposes;
Aquaculture facilities;
Beach nourishment;
Waterborne passenger transportation facilities such as those serving ferries, cruise ships, commuter and excursion boats, and water shuttles and taxis;
Dredging for navigation channels, boat basins, and other water-dependent purposes and subaqueous disposal of the dredged materials below the low water mark;
Navigation aids, marine police and fire stations, and other facilities which promote public safety and law enforcement on the waterways;
Shore protection structures, such as seawalls, bulkheads, revetments, dikes, breakwaters, and any associated full which are necessary either to protect an existing structure from natural erosion or accretion, or to protect, construct, or expand a water-dependent use;
Flood, water level, or tidal control facilities;
Discharge pipes, outfalls, tunnels, and diffuser systems for conveyance of stormwater, wastewater, or other effluents to a receiving waterway;
Marine terminals and related facilities for the transfer between ship and shore, and the storage of bulk materials or other goods transported in waterborne commerce;
Facilities associated with commercial passenger vessel operations;
Commercial fishing and fish processing facilities;
Boatyards, dry docks, and other facilities related to the construction, serving maintenance, repair, or storage of vessels or other marine structures; and
Other industrial uses or infrastructure facilities which cannot reasonably be located at an inland site.
III-C-4. Municipal Harbor Plans
In September 1990 the Secretary of Environmental Affairs adopted regulations for "Review and Approval of Municipal Harbor Plans" (301 CMR 23.00). The regulations established a voluntary procedure by which municipalities could obtain state approval of a municipal harbor plan.
A municipal harbor plan is defined as a document setting forth the community's
objectives, standards, and policies for guiding public and private use
of the land and water areas of a harbor and an implementation program to
achieve the desired plan.
A plan prepared and approved in accordance with these regulations serves
to guide EOEA agency actions, including the regulatory decisions of the
Department of Environmental Protection under M.G.L. Chapter 91. When an
approved harbor plan exists, any project seeking a Chapter 91 permit from
DEP must be in conformance with that plan . In essence, a municipality
with an approved harbor plan utilizes the state regulatory authority to
help implement its own objectives.
Through a locally-prepared harbor plan, a municipality has the ability
to "substitute" local standards for certain state Chapter 91 requirements
such as building height limits and to "amplify" certain discretionary state
standards.
The standards that can be substituted by an approved harbor plan apply only to nonwater-dependent uses. Section 9.51(3) establishes minimum standards and limitations on building height, site coverage, waterfront setback, and encroachment into flowed tidelands. Section 9.53(2)(b)-(c) pertains to the provision of interior and exterior public space in a project. Section 9.52(1)(b)(1) is a requirement for a waterfront walkway with a minimum width of 10 feet to be included with any non water-dependent use. In those instances where non water-dependent uses are allowed, this public access requirement exists, as does the ability to modify it through a municipal harbor plan.
The provisions of a municipal harbor plan can also be effective in providing guidance for DEP in applying the numerous discretionary requirements of the Chapter 91 regulations to projects under review.
III-C-5. Federal Emergency Management Act Regulations
The Federal Emergency Management Agency (FEMA) performed a Flood Insurance Study of the Town of Provincetown in 1983. The study utilized hydrologic and hydraulic analyses to establish Flood Insurance Zones and flood plain management measures for the area. The investigation considered historic flood elevations and estimates of shoreline levels considering stillwater and wave runup for various frequency storms. The major past storms of the area occurred in February 1978, December 1959, August 1954, and September 1938. The February 1978 nor'easter produced water levels higher than any others ever recorded.
The FEMA Flood Zones Map provides a plan of the various Flood Insurance
Zones along the harbor as established by this study. The following provides
a further description of the zone designation:
Zone A: Special Flood Hazard Areas inundated by various types of 100-year
shallow flooding, determined by approximate methods; no flood elevations
shown or flood hazard factors determined.
Zones A2 & A4: Special Flood Hazard Areas inundated by the 100-year
flood, base flood elevations shown, and zones subdivided accordingly.
Zones V2 and V4: Special Flood Hazard Areas along coasts inundated
by the 100-year flood that have additional hazards due to velocity (wave
action of 3 foot amplitude or greater); base flood elevations shown are
subdivided according to flood hazard factors.
Zone B: Areas between the Special Flood Hazard Area and the limits
of the 500-year floodplain that are protected from the 100-year flood by
dike, levee, or other water control structure; also, areas subject to certain
types of 100-year shallow flooding where depths are less than 1 foot; and
areas subject to 100-year flooding from sources with drainage areas less
than 1 square mile. Zone B is not subdivided.
Zone C: Areas of minimal flooding.
An evaluation of FEMA zones indicates that only portions of several buildings are in the V Zone to the west of MacMillan Pier . Also, no portion of the V Zone crosses Commercial Street within this area. To the east of MacMillan Pier , essentially all buildings seaward of Commercial Street have some portion within the V Zone. Further, approximately 41,000 linear feet of Commercial Street is located within a V Zone in this area. These conditions have been mapped in the associated figure (see Figure 7. Existing Development within FEMA Velocity Zones); please note that this map is for planning purposes only, and FEMA maps should be directly consulted regarding any individual property.
Chapter I: MacMillan Pier Regulations
All the vessels, persons, and vehicles using the pier are governed by these rules and all other laws, by-laws, or court orders from such agencies as the US Coast Guard, the EPA, DEP, the Commonwealth of Massachusetts or the Town of Provincetown.
The Harbormaster has authority and responsibility for daily operation
and management of the pier and the adjacent waters, and must be consulted
on matters pertaining to the use and operation of the pier. The pier shall
be open 24 hours a day for use by licensees, transient vessels and the
general public.
MacMillan Pier is primarily for the use and benefit of commercial fishing vessels, commercial passenger vessels, and for the passive enjoyment of the general public. All commercial users of the pier are required to have a license from the town. All other uses (except those enumerated in this section) are prohibited unless expressly authorized by the Board of Selectmen or delegates.
The use of the easterly finger piers is restricted to active, full-time,
year-round commercial fishing vessels. Use of the pier by vessels on a
transient basis to load and unload gear, supplies, etc. shall be accommodated
on a first-come first-serve basis, based on the time-limits set by the
Harbormaster.
Passenger vessels may use the pier for loading and unloading of passengers
only under agreement with the town and in the specified locations in that
agreement. The Licensing Board is responsible for issuing licenses to said
vessels.
The pier is open to the public 24 hours a day and pedestrian access
is restricted to within the curbed sidewalk along the west side of the
pier. Recreational fishing is prohibited except in those areas designated
by the Harbormaster. Vehicles on the pier are limited to those actively
serving the vessels and businesses on the pier and casual traffic by the
general public. No vehicles are allowed to enter, leave, or move within
the Outer Tee area while pedestrians are exiting the Boston passenger vessel.
The regulations also establish limits on the weight allowed on the pier
and on the Outer Tee.
A license or permit from the town is required for permanent berthing
of vessels and placement of floats. An annual or semi-annual dockage permit
issued by the town is required from commercial fishing vessels that regularly
use the pier. These permits are issued based on the approval of the Board
of Selectmen or delegates and upon payment of the required fee. Vessels
not having a permit may use the pier, but are required to pay a transient
vessel fee.
Any seafood off-loading or handling on the pier requires a license issued from the Licensing Board. The Board may designate Transient Seafood Off-loading Space, and issue licenses for the space. Off-loading without a permit is allowed adjacent to a leased docking a