Sewer Expansion Construction Ongoing

Homepage News Story Images (45)

UPDATE - Week of March 4, 2024:

Beginning Monday, March 4, crews will be working on Kendall Lane, Bradford St. (between Court St. and Prince St.), Wareham St, Race Rd., Bangs St., Alden St., Standish St. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Court St.
  • Winthrop St.

UPDATE - Week of February 26, 2024:

Beginning Monday, February 26, crews will be working on Wareham St., Ships Way Rd., and Atlantic Ave. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Wareham St.
  • Bradford St. at Kendall Lane
  • Bradford St. (between Court St. and Prince St.)
  • Bangs St.
  • Alden St.

UPDATE - Week of February 19, 2024:

Beginning Monday, February 19, crews will be working on Alden St., Bradford St. (between Kendall Lane and Conway St. and between Court St. and Prince St.), Capt. Bertie's Way, Bangs St., and Bradford St. (between Kendall Lane and Conway St. and Court St. and Prince St.). After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Wareham St.
  • Ships Way Rd. Ext.
  • Atlantic Ave.
  • Alden St.

UPDATE - Week of February 12, 2024:

Beginning Monday, February 12, crews will be working on Atlantic Ave., Court St., Capt. Bertie's Way, Ships Way Rd., Bangs St., and Atlantic Ave. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Court St.
  • Winthrop St.

UPDATE - Week of February 5, 2024:

Beginning Monday, February 5, crews will be working on Atlantic Ave., Court St., Bradford St. (between Brewster St. and Howland St. and between Kendall Lane and Conway St.), and Bangs St. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Court St.
  • Winthrop St.
  • Bradford St. (between Kendall Lane and Conway St.)
  • Bangs St.
  • Bradford St. (between Court St. and Prince St.)

UPDATE - Week of January 29, 2024:

Beginning Monday, January 29, crews will be working on Ships Way Rd Ext., Atlantic Ave, Alden St, and Bradford St. (Brewster St. to Howland St.). After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Bradford St. (Brewster St. to Howland St.)
  • Jerome Smith Rd.
  • Bangs St.

UPDATE - Week of January 12, 2024:

Beginning Monday, January 22, crews will be working on Carnes Lane, Atlantic Ave., Alden St., Standish St., Cemetery Rd., and Ships Way Rd. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Ships Way Rd.
  • Court St.
  • Bradford St (between Priscilla Alden Rd. and Kendall Lane)

UPDATE - Week of January 15, 2024:

Beginning Monday, January 15, crews will be working on Kings Way, Bradford St (between Shank Painter Rd. and Prince St.), Shank Painter Rd., Atlantic Ave., Holway Ave., Capt. Berties Way, Carnes Lane, and Court St. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Atlantic Ave.
  • Mozart Ave.
  • Court St.
  • Ships Way Rd.

UPDATE - Week of January 8, 2024:

Beginning Monday, January 8, crews will be working on Winthrop St, Court St., Watsons Court, Race Road, and Bradford St (between Montello St. and Prince St) and then move to Shank Painter Road. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Shank Painter Rd.
  • Jerome Smith Rd.
  • Cudworth St.
  • Holway Ave.
  • Capt. Berties Way
  • Ships Way Rd.
  • Carnes Lane.

UPDATE - Week of January 1, 2024:

There will be no work on Monday, January 1. Beginning Tuesday, January 2, crews will be working on Race Road and Bradford St (between Montello St. and Prince St) as well as Atlantic Ave., Central St., and Winthrop St. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Bradford St. at Shank Painter Rd.
  • Court St.
  • Watsons Ct.
  • Cudworth St.
  • Holway Ave.
  • Captain Berties Way
  • Ships Way Rd.

UPDATE - Week of December 25, 2023:

There will be no work on Monday, December 25. Beginning Tuesday, December 26, crews will be working on Browne St. and Race Road. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Bradford St. (between Montello St. and Pine St.)
  • Carnes Lane

UPDATE - Week of December 18, 2023:

Beginning Monday, December 18, crews will be working on Montello St., Conant St., Fritz's Way, and Browne St. After work in these locations is complete, crews will be working on the following streets during the next 3 weeks:

  • Browne St.
  • Race Rd.
  • Carnes Lane

UPDATE - Week of December 12, 2023:

Beginning Monday, December 11, crews will begin paving on Franklin St, Race Road, and Pleasant St. They will continue with sewer work on Pleasant St. Carnes Lane, and Montello St. After work in these locations is complete, crews will begin working on the following streets during the next 3 weeks:

  • Montello St.
  • Conant St.
  • Browne St.
  • Kings Way
  • Fritz's Way

UPDATE - Week of December 4, 2023:

Beginning Monday, December 4, crews will start work on Snows Lane. They will then work their way to Pleasant St. followed by Race Rd (between Franklin St. and Pleasant St.) After work in these locations is complete, crews will begin working on the following streets during the next 3 weeks:

  • Race Road
  • Carnes Lane
  • Montello St.

The Town of Provincetown, along with the Town's contractor the Robert B. Our Company (RBO), will be begin Phase 6 sewer expansion work on Tuesday, November 28. 

RBO will begin installing new sewer connection stubs to properties on Franklin Street. This work is expect to last most, if not all, of the week. Once Franklin St. work is complete, crews will move to Pleasant Street and Montello Street. We do not anticipate needing to close the road fully during this work, but please expect detours and delays as the crews work. There will be police details working with construction crews to assist with traffic. 

Please keep in mind:

  • Schedules change.
  • Work does not always go as planned.
  • Weather does not always cooperate.
  • Issues can occur during construction work.

Should an incident occur during the work, Provincetown DPW will post information on their Facebook page. If an emergency occurs, the Town will send out information via the Town’s emergency alert system. Not signed up for alerts? Click here to register. 

As sewer construction advances, DPW staff will work closely with our engineering and construction contractors to provide residents with up to date information. The Town has also launched a new page to share information and updates on the sewer expansion project at www.provincetown-ma.gov/1464/Sewer-Expansion-Project.

On this page you will find:

  • Information on stub locations for your sewer connection if part of Phase 6.
  • A link to sign up for email/text notifications on Phase 6 work.
  • Information on betterments and financial assistance (coming soon).
  • Other important information as the project progresses.

Those with questions or concerns should contact Sherry Prada, DPW Deputy Director, or Braden Witt, Sr. Project Manager, at 508-487-7060. Thank you in advance for your cooperation and understanding during this important sewer expansion work.

Facebook Twitter Email

Other News in Home Page

Homepage News Story Images (60)

Proposed FY2025 Budget

Posted on: January 24, 2024
Homepage News Story Images (57)

Winter Weather Preparedness Tips

Posted on: January 4, 2024
Register Your Rental

Register Your Rental

Posted on: August 4, 2023